Who is responsible for the Yuanshanzi Flood Diversion Road?

Who is responsible for the Yuanshanzi Flood Diversion Road?

    In 1963, the Taiwan Provincial Water Conservancy Bureau first proposed it in the Taipei area flood control plan. I can't find the proposed document at that time. The person who came up with the idea should be given the first credit.
    In 1970, the Water Resources Unified Planning Committee of the Ministry of Economic Affairs reviewed the case and proposed measures. However, the priority was given to regulating the Tamsui River at that time and it was not adopted.
    In 1987, Typhoon Lynn's torrential rains caused widespread flooding in the Keelung River. Superiors instructed the Taiwan Provincial Water Conservancy Bureau to re-develop the Shanzi Flood Diversion Channel. The superior at that time should be given second credit. The executive president at that time was Yu Guohua, and the governor of Taiwan was Qiu Chuanghuan.
    In 1989, the instructional research report was released, but it still recommended that Keelung River flood control be prioritized first, and then flood diversion.
    In 1998, during this period, the flood control effect of the Keelung River was not effective. The Executive Yuan instructed the Ministry of Economic Affairs to integrate various responsible units to handle - Keelung River overall management plan planning work - The Executive President is Xiao Wanchang
    In 2000, the Water Resources Department of the Ministry of Economic Affairs completed the plan report. However, the Keelung River regulation plan proposed by the Water Resources Department of the Ministry of Economic Affairs required a flood control cost of 105 billion yuan and required the demolition of thousands of residential houses. Instructions from the Executive Yuan: Priority should be given to the feasibility of promoting the Yuanshanzi flood diversion project - the Executive Yuan is Xiao Wanchang, who should be given the second credit
    In 2000, the Water Conservancy Department of the Ministry of Economic Affairs completed the renovation plan, and the Executive Director ordered to immediately promote the work related to the Yuanshanzi Flood Diversion Project - the Executive Director is Zhang Junxiong, who is the third creditor
    In 2001, United Dadi signed a contract with Juting (Engineering) Co., Ltd., and construction started in 2002 and was completed in 2005, costing 6 billion yuan. Both companies were rewarded for their hard work without credit. Hmm~ So are the employees of the Water Resources Department and Bureau!
    In 2004, Yuanshanzi flood diversion channel was opened
    In 2017, it was the 40th flood diversion after it was put into use.
    In 2024, Typhoon Kemi, 0921 Heavy Rain, and Typhoon Shantuoer have diverted floods three times

旅人央紗@Youtube
. email: [email protected]
旅人首頁 國家旅景 旅景文全列 好玩的地方排行榜
T:0000
資訊與搜尋 | 回trip首頁 | 回taiwan首頁
email: Yan Sa [email protected] Line: 阿央
電話: 02-27566655 ,03-5924828
阿央
泱泱科技
捷昱科技泱泱企業